JOHNSON, J.
The petitioner, Ashland Electric Department, (Ashland) appeals an order by the New Hampshire Public Utilities Commission (PUC) denying Ashland's request for a declaratory ruling that it may expand its distribution facilities within the Town of Ashland (town) without the PUC's authorization and requiring Ashland to follow the administrative procedures set forth in RSA chapter 38 before undertaking that expansion. We affirm.
The following findings...