This is a contract dispute between a public utility and a cogeneration company developing a hydroelectric facility. We conclude that the trial court should not have granted summary judgment in favor of the utility because a question exists whether there has been an event of force majeure that would excuse the cogenerator from its failure to post a contractually required security bond.