The opinion of the court was delivered by STERN, J.A.D.
Defendant Village of Ridgefield Park appeals from a judgment of the Law Division entered on December 9, 1994 declaring plaintiff the low bidder and awarding a contract to it. We reverse.
The Village declared defendant Montana Construction Company the lowest responsible bidder on the contract for installation of a "storm drainage bypass system." Montana submitted a bid of $363,255.00. Plaintiff had also...