Plaintiff waived its claims against the City for extra and additional work allegedly performed by failing to comply strictly with the notice and documentation provisions in Articles 27 and 28 of the parties' contract. These provisions required the contractor to notify the Commissioner promptly, in writing, that the work directed to be done was extra work and request a final determination from the Commissioner, and also required contemporaneous written detailed documentation...