In January 1990, claimant entered into a contract to perform roofing work on several buildings owned by the State. The contract provided that if the work was not "physically completed" within 204 days — later extended to 209 days — the payment due claimant would be reduced by $100 for every day of delay. The contract also stated that claimant was directed not to perform "the roofing and related [w]ork" between December 1...