Ordered that the judgment is affirmed, with costs.
The plaintiff contractor and the defendant Town of Islip entered into a written contract for the reconstruction of the Bay Shore Marina Bulkhead. The contract provided that the contractor's acceptance of final payment from the Town released the Town from all claims the contractor might have had in connection with the contract. After the contractor filed a notice of claim against the Town for delay damages, he cashed...