Defendant contracted to build an improved basement, with concrete block walls and a poured concrete floor, beneath plaintiffs' house for a total price of $8,700. $4,000 was to be paid upon signing the contract, $2,700 when the work was three fourths completed, and the final $2,000 upon completion. The first two payments were made and the work progressed, but prior to its completion a dispute arose between plaintiffs and defendant, and...