GREENE, Judge.
The defendant appeals from a judgment entered 15 February 1990 ordering the defendant to pay $18,000 to the plaintiffs on their claim for the negligent construction of a pool.
In May of 1987, the plaintiffs contracted with the defendant for the construction of a swimming pool on the plaintiffs' property for $12,000. When the pool was roughly 80% completed, the plaintiffs paid the defendant the contract price. After the pool was filled with water...