PARKER, District Judge:
BACKGROUND
On October 29, 1971, the City of New Haven (the City) and Camp, Dresser & McKee, Inc. (CDM) entered into a contract in which CDM agreed to provide the complete design for the East Shore Wastewater Treatment Plant (the plant).
The design of the plant involved "process design" and "non-process design." The former included design of the machinery, equipment and systems necessary to treat sewage. Non-process design...