SHORTESS, Judge.
Firmin, Inc. (Firmin), was the general contractor for the construction of Live Oak Middle School for the Livingston Parish School Board pursuant to a written contract signed by these parties on May 24, 1983. Alvin Fairburn and Associates, Inc. (Fairburn), was the design architect. Firmin subcontracted the floor covering work to Denham Springs Floor Covering, Inc. (DSFC).
Construction of the school began around June 3, 1983. The concrete slab...