Petitioner contends that, as a result of the failure of the Town of Saugerties Planning Board in Ulster County to act on her application for subdivision approval within 45 days after the public hearing, the application must be approved by default under Town Law § 276 (4). Supreme Court held that the 45-day period did not begin to run because petitioner's application was not complete. The petition was therefore dismissed, resulting in...