In 1980, Spearin and the City entered into a contract, pursuant to which Spearin was to perform certain general construction work in connection with the reconstruction of the Wollman Memorial Ice Skating Rink in Central Park. In December 1980, Spearin commenced the work which, under the terms of the contract, was to be completed within 270 calendar days.
Although 60% of the work was completed in 66% of the time alloted, the balance was not completed until June 1983...