PER CURIAM.
Appellants, defendants in an action on a construction contract, are correct in all three issues raised by this appeal from an adverse judgment.
First, in the absence of an agreement fixing the rate of interest in the event of an action to enforce the contract, the statutory interest rate applies. Celotex Corp. v. Buildex, Inc.,