FEHRINGER v. THOMAS CRIMMINS CONTRACTING CORP.


167 A.D.2d 982 (1990)

William F. Fehringer, P.C.S., P. C., Appellant, v. Thomas Crimmins Contracting Corp., Respondent

Appellate Division of the Supreme Court of the State of New York, Fourth Department.

November 16, 1990


Order unanimously reversed on the law with costs, motion granted and cross motion denied.

Memorandum:

The court erred in denying plaintiff's motion for summary judgment and in granting defendant a conditional order of preclusion (CPLR 3042 [c], [e]). Plaintiff served a summons and verified complaint, dated June 8, 1989, alleging causes of action for breach of contract and account stated, and demanding judgment in the amount of $49,425.25. With its answer of...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases