PER CURIAM.
The appellant/contractor appeals a ruling of the construction licensing board. We reverse and remand with direction.
Appellant entered into a contract to build an addition to James Courim's home. After completion of the construction, a dispute arose and Courim filed a cause of action against appellant and obtained a judgment for $38,841.94 against the appellant.
Thereafter, in November, 1987, Courim filed a complaint against appellant with...