WILNER, Judge.
The issue before us is whether the Circuit Court for Anne Arundel County erred in concluding that the underlying dispute between the parties was not within the scope of a contractual arbitration clause. We think that it did so err.
Regina Construction Corporation, a Nevada corporation having its principal office in Virginia, was the general contractor on a construction project in Washington, D.C. In June, 1984, Envirmech Contracting Corporation...