The defendant is the owner and developer of two office buildings. Plaintiff entered into similar net leases for building number 1 on May 1, 1982 and for building number 2 on May 20, 1982. A violent storm blew a portion of the roof off building number 2 in April 1987. In November 1987, plaintiff's engineers determined both roofs had not been constructed according to specifications. Plaintiff initiated arbitration to resolve a dispute over who was to pay for repairs of the...
Let's get started
Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.
- Updated daily.
- Uncompromising quality.
- Complete, Accurate, Current.