BRAMCON GEN. CONTRACTORS, INC. v. WIGLEY CONST. CO.

No. 08-89-00102-CV.

774 S.W.2d 826 (1989)

BRAMCON GENERAL CONTRACTORS, INC., Appellant, v. WIGLEY CONSTRUCTION COMPANY, Appellee.

Court of Appeals, of Texas, El Paso.

July 5, 1989.


Attorney(s) appearing for the Case

Steven E. Kennedy, Canterbury, Stuber, Elder & Gooch, Dallas, for appellant.

Thomas A. Shiels, Matthews, Carlton & Stein, Dallas, for appellee.

Before FULLER, WOODARD and KOEHLER, JJ.


OPINION

FULLER, Justice.

Summary judgment was granted in favor of a subcontractor for the balance due under a contract with the general contractor. We affirm.

Appellee Wigley Construction Company was a subcontractor under a written contract with the contractor Appellant, Bramcon General Contractors, Inc. The total contract price was $173,000.00. Appellee had been paid a total of $143,769.92 when this controversy arose as to the remaining balance...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases