HALL, Judge.
The appellant challenges the nonfinal order which grants the appellees' motion to compel arbitration. He argues that the trial court erred in failing to conduct a full evidentiary hearing on the issue of whether the contract between the appellant and the appellees contained an arbitration provision. We affirm.
In June 1987 the parties entered into a contract to construct an office building in Hillsborough County. Subsequently, the parties modified...