Order modified on the law and as modified affirmed without costs, in accordance with the following memorandum: Plaintiff was the low bidder on a public improvement contract on Alexander Street in the City of Rochester, and it was awarded the contract. It considered rock removal to be a small portion of the job, and it bid $25 per cubic yard to excavate rock, an amount which was below the actual cost. Job drawings, prepared by codefendant Passero, showed only about 20 cubic...