DAVID CO. v. JIM W. MILLER CONST., INC.

No. C6-88-327.

428 N.W.2d 590 (1988)

DAVID COMPANY, Respondent, v. JIM W. MILLER CONSTRUCTION, INC., Appellant.

Court of Appeals of Minnesota.

Review Granted October 26, 1988.


Attorney(s) appearing for the Case

Sue R. Halverson, Hart, Bruner & O'Brien, P.A., Minneapolis, for respondent.

Ronald E. Martell, Moore, Costello & Hart, St. Paul, for appellant.

Heard, considered and decided by SCHUMACHER, P.J., and RANDALL and MULALLY, JJ.


OPINION

EDWARD D. MULALLY, Judge.

Respondent David Company (David Co.) demanded arbitration of its claim of breach of a construction contract against Jim W. Miller Construction, Inc. (Miller). The arbitrators awarded David Co. damages of $884,476 and awarded Miller the property in issue. David Co. applied for confirmation of the arbitration award and Miller applied for vacation of the award.

The trial court confirmed the arbitration award and ordered...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases