FRIEDMAN, Circuit Judge.
This is an appeal from a judgment of the United States Claims Court rejecting the appellant's claim for an equitable adjustment of its contract price based upon two claims: that the site conditions it found in performing the contract were different from those stated in the specifications, and that the specifications were defective. The Claims Court rejected both contentions. Stuyvesant Dredging Co. v. United States, 11 Cl.Ct. 853 (1987...