CRIST, Judge.
Appeal from an award of $30,000 in damages for breach of a written construction contract entered into by the parties on April 29, 1971. We affirm.
Appellant (contractor) constructed a dorm addition using the second floor of respondent's (owner) residence. Work began on April 10, 1971, and was concluded on May 18, 1971. Owner testified that, beginning in 1977, she noticed cracks and ceiling splits on the first floor level and a sagging floor in...