Order affirmed, with costs.
The instant action involves a contract entered into by the plaintiff and the defendant Sea Crest Construction Corp. (hereinafter Sea Crest) in July 1976 for the construction of a solid waste treatment facility. The contract originally provided that the project would be completed within 550 days and that time was of the essence. The parties subsequently agreed