LANSING, Judge.
Orr-Schelen-Mayeron & Associates, Inc. (OSM), an engineering firm, prepared specifications for a municipal public works project. Waldor Pump & Equipment Co., subcontractor and supplier to Paul A. Laurence Co. (PALCO), the general contractor, alleged OSM was negligent after Waldor Pump's equipment was rejected as not conforming to specifications. The jury found OSM negligent in drafting and interpreting specifications. OSM...