The opinion of the court was delivered by
McFARLAND, J.:
This is a dispute between plaintiff J.A. Tobin Construction Co. and defendant Secretary of Transportation concerning which should bear the cost of corrective work on a defective concrete culvert.
Plaintiff was the general contractor on a highway construction project. As a part of its performance under the contract, plaintiff (through a subcontractor) constructed a concrete box culvert. The contract...