RABINOWITZ, Chief Justice.
OPINION
This appeal arises out of an action which was brought by a sub-subcontractor to recover on a prime contractor's surety bond, for materials it used in performing its sub-subcontract. At issue is whether the sub-subcontractor can recover for materials when the bonded contract bound the prime contractor to furnish labor only.
FACTS.
In June 1979, the North Slope Borough ("NSB") entered into a contract with...