OXBERGER, Chief Judge.
The plaintiff appeals from the trial court's rulings in two consolidated actions to recover moneys in connection with a construction contract. We affirm the trial court in part and reverse in part regarding the court's failure to award interest on a portion of the moneys paid.
Plaintiff Ida Grove Roofing and Improvement, Inc. submitted the lowest bid for a contract to replace the roof of the city water works plant. The project included...