HILTON N.J. CORP. v. ATLANTIC CITY ELEC. CO.


205 N.J. Super. 217 (1985)

500 A.2d 728

IN THE MATTER OF THE HILTON NEW JERSEY CORPORATION, PETITIONER-APPELLANT, AND IN THE MATTER OF THE GOLDEN NUGGET ATLANTIC CITY CORPORATION, PETITIONER-APPELLANT, v. ATLANTIC CITY ELECTRIC COMPANY, RESPONDENT.

Superior Court of New Jersey, Appellate Division.

Decided November 8, 1985.


Attorney(s) appearing for the Case

Brian D. Spector argued the cause on behalf of appellant Hilton New Jersey Corporation (Ribis, McCluskey, Ruane & Graham, attorneys; Connell, Foley & Geiser, attorneys; Adrian M. Foley, Jr., of counsel; Kevin J. Coakley, Keith A. Krauss and Jacqueline Chasey on the brief).

Stephen M. Holden argued the cause on behalf of appellant Golden Nugget, Atlantic City Corporation (Greenberg, Margolis, Ziegler & Schwartz, attorneys; Jeffrey D. Light of counsel and on the brief).

Daniel P. Duthie, admitted pro hac vice, argued the cause on behalf of respondent (Holzapfel, Perkins & Kelly, the New Jersey partner in the firm of LeBoeuf, Lamb, Leiby & MacRae, attorneys; William R. Holzapfel, Jeffrey W. Meyers, Michael W. Youkon and Mr. Duthie of counsel; Mr. Holzapfel on the brief).

Joseph L. Yannotti, Deputy Attorney General, attorney for the Board of Public Utilities (Irwin I. Kimmelman, Attorney General, attorney; James J. Ciancia, Assistant Attorney General, of counsel; Alan S. Pralgever, Deputy Attorney General, on the brief).

Diana Johnston, Deputy Public Advocate, argued the cause for the Division of Rate Counsel (Amy R. Piro, Acting Public Advocate, attorney; Arthur Penn, Special Counsel, on the brief).

Nicholas I. Filocco argued the cause on behalf of appellant-intervenor Bally's Park Place, Inc. (Waters, McPherson & McNeil, attorneys).

Before Judges FURMAN, PETRELLA and ASHBEY.


The opinion of the court was delivered by FURMAN, P.J.A.D.

Hilton New Jersey Corporation (Hilton) and Golden Nugget Atlantic City Corporation (GNAC) appeal from an order of the Board of Public Utilities (BPU) imposing upon them the cost of extension of Atlantic City Electric Company (ACE) transmission lines to serve their new casino hotel projects in the Atlantic City Marina area. Bally's Park Place, Inc. intervenes in support of Hilton's and GNAC's appeals.

...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases