Heard Jan. 21, 1985.
Decided May 7, 1985.
CHANDLER, Justice:
Appellant Hunter Brothers Systems, Inc. (Hunter) subcontracted with the general contractor, Respondent Brantley Construction Company, Inc. (Brantley), to perform the electrical work on a warehouse (project) for State Ports Authority (Owner) at its Wando Terminal.
Upon completion of the project Brantley refused to pay Hunter the remaining $72,161.00 balance of the contract price. Brantley...