Judgment modified, on the law, to the extent that the appellants are directed to award the contract to petitioner at the negotiated bid price of $131,224,741. As so modified, judgment affirmed, with costs to petitioner.
Appellants received three bids on the "Zone II Contract" to perform extensive rehabilitative and reconstructive work on a portion of New York City's subway system. Petitioner was the lowest bidder, with a bid falling within the advertised estimate...