WENTWORTH, Judge.
Appellant seeks review of an order by which a claim on a construction payment bond was denied, but damages were awarded for a breach of contract by appellee Snavely. We find that the trial court did not err in denying the claim on the bond, but the cause must be remanded for a redetermination as to the amount of damages occasioned by Snavely's breach of contract.
Appellant was a subcontractor, and appellee Snavely the general contractor,...