JOSEPH, Chief Judge.
This is a legal malpractice case. In a trial without a jury, the court found defendant negligent in failing to bring a foreclosure action on two mechanic's liens within the six-month time period prescribed in ORS 87.055. Plaintiff, the lienor, was awarded the amount of those liens, $15,897.15, as damages. We affirm.
Plaintiff sent the lien documents to defendant in January and February, 1980, and instructed him to protect its interests...