GIBSON, Justice.
This appeal, after trial by jury in Bennington Superior Court, arises from a contract dispute involving the construction of defendant's residence. Plaintiff is a building contractor who seeks $10,912.57 that he alleges is the outstanding balance for time and materials owed. Defendant counterclaimed, alleging damages for unfinished and defective construction. The jury returned a verdict in the full amount sought by plaintiff and found no liability...