Judgment unanimously reversed, on the law, without costs, and judgment granted in favor of plaintiff declaring the completion date to be March 31, 1985.
Memorandum:
In this action on submitted facts (CPLR 3222), the dispute concerns the completion date for the general construction work for the Rochester Convention Center. After competitive bidding, plaintiff, City of Rochester, awarded the general construction contract to defendant, LeCesse Bros. Contracting...