Defendant engaged MacNutt Electric Co., Inc. to perform the electrical contracting work in connection with the construction of the 43rd Precinct station house. Although the original completion date was September 1, 1973, the work was not completed until June, 1975. On May 14, 1975, the city, through its Bureau of Building Construction, issued its certificate of completion and acceptance. The certificate reflected that the total amount payable to MacNutt under the provisions...