PER CURIAM:
The People's Counsel challenges an order of the Public Service Commission granting Potomac Electric Power Company a permanent rate increase of $35,465,000 on the following bases: 1) the Commission's failure to permit untimely filed testimony as to possible modifications in PEPCO's management and construction program; 2) the Commission's failure to set the new rate at the lowest end of the "zone of reasonableness"; 3) the Commission's failure to consider...