This dispute centers around whether Amoco is responsible for the payment, as a penalty cost, of 200% of the total cost of construction of a gas pipeline as claimed by Texaco, or 200% of Amoco's 25% share of the construction of the line.
The trial judge, by summary judgment, concluded that Texaco was entitled to recover 200% of the total cost of construction. Amoco appeals. We affirm.
Amoco...