SUTIN, Judge.
Horn appeals from a judgment in favor of Henthorn in the sum of $2,960.71. We affirm.
The trial court found:
1. That by contract executed on July 2, 1978, Henthorn agreed to construct a house for Horn for a consideration equal to cost plus 30% but not to exceed $63,280.
2. Subsequently, construction began, certain extras had been agreed to by the parties, and as of January 8, 1979, Horn had paid Henthorn $70...