NORTHWEST PIPELINE v. FORREST WEAVER FARM

No. 13701.

646 P.2d 422 (1982)

103 Idaho 180

NORTHWEST PIPELINE CORPORATION, Plaintiff-Respondent, v. FORREST WEAVER FARM, INC., an Idaho Corporation, Defendant-Appellant.

Supreme Court of Idaho.

June 10, 1982.


Attorney(s) appearing for the Case

Leon R. Weeks (deceased), Nampa, for defendant-appellant.

Gary L. Montgomery, of Marcus & Marcus, Boise, for plaintiff-respondent.


McFADDEN, Justice.

On June 3, 1955, Earl and Darlene Clark executed a contract which granted to Pacific Northwest Pipeline Corporation and its successors and assigns "the right to select the route for and construct, maintain, inspect, operate, protect, repair, replace, alter or remove a pipeline or pipelines for the transportation of oil, gas and the products thereof, on, over and through (grantors property)." The consideration...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases