Order reversed, with $50 costs and disbursements, and motion denied.
The counterclaim in question asserts a cause of action to recover against an architect for breach of contract or for professional malpractice. Under either theory the board's claim accrued on the date of completion of the project which was the subject of the architectural contract between the parties and the consequent termination of their professional relationship thereunder (Sosnow v Paul