KASS, J.
Under G.L.c. 30, § 39K, a public body must pay to the contractor on a public construction job the amount of the final payment requisition within sixty-five days after the contractor fully completes the work. We hold that the town of Rockport, whose specially retained engineer had approved a final requisition in writing, is liable for the balance of the construction contract in the absence of facts indicating that the engineer's approval was made "in...