SATZ, Presiding Judge.
In this cause, Sunny Baer Co., Inc., sued defendants, William and Ossie Slaten, for breach of contract. Under the terms of the contract, plaintiff was to repair defendants' fire-damaged building for $4,800. Defendants paid plaintiff only $2,500. In its suit, plaintiff alleged complete performance of the contract and sought the $2,300 balance due on the contract price.