SUMMERS, Chief Justice.
This is an appeal from a take-nothing judgment in a general contractor's suit for damages allegedly resulting from a breach of a construction subcontract.
Appellant Harry Brown, Inc. (Brown) was the general contractor employed by the Sabine Independent School District, Gladewater, Texas, for the construction of an expansion to the Sabine Elementary School in Liberty City, Texas. On or about May 15, 1978, Brown entered into a subcontract...