CAPORALE, District Judge.
This is an appeal from an order of the Nebraska Power Review Board (Board) granting an application of the Lincoln Electric System (LES). We affirm.
The appeal asks, as a question of first impression, whether the authority of the Board to find that construction of a transmission line will serve the public convenience and necessity carries with it the power to select the particular route the line must follow. Stated another way, the...