For reasons stated herein we conclude that the trial court erred in denying the State's motion for permission to serve a counterclaim and thereafter in refusing to permit the State to introduce evidence tending to show that much of claimant's claim for extra work was performed only to cure design defects which were its own responsibility and not recoverable under its contract with the State; that the...