The issue we decide in this interlocutory transfer is whether the defendant towns may require the plaintiff to use underground transmission lines after the public utilities commission has issued to the plaintiff a certificate of site and facility authorizing above-ground transmission lines for the Seabrook Nuclear Electric Generating Station, in compliance with RSA ch. 162-F. We hold that the towns lack power to...