PER CURIAM.
This is an appeal by appellant, a subcontractor, from an amended final judgment allowing the appellee, a materialman, to recover $18,960.40, plus interest, on its statutory lien.
Appellants first allege that the trial court committed error in concluding that the materials allegedly delivered by appellee were in fact delivered or incorporated in the subject real property. Materialmen are entitled to perfect a mechanic's lien against the property...