Eight consecutive waivers of claims theretofore existing against defendant-appellant city were executed by plaintiff-respondent "waiving and releasing all claims which it may have against the city * * * arising out of the aforesaid". We construe the word "aforesaid" to refer to the entire contract and not merely to the time extension caused by delay in removal of the existent installation. We observe that the letter on plaintiff's stationery in and by which the claims were...