PONDER, Judge.
Plaintiff appealed from the judgment dismissing its claim for increased payment on a contract.
The issue is the validity of the holding that defendant was not liable beyond the contracted price.
We affirm.
Plaintiff bid on some electronic equipment for a ship defendant was building on contract. Defendant used this bid in entering into the contract. Seven months later plaintiff advised defendant of an increase in prices. Defendant...